Our service team participated in service work on the compressor delivered and installed to Otvice compression station which is a part of the Capacity4Gas project. We have applied our experience and proven our high competencies when replacing filters, sumps and tightening flange connections in the area of correct tightening of flange joints, where our technicians used mainly hydraulic and electric tighteners of the American company Hytorc.
More about the project:
Capacity4Gas is the largest gas project of recent years of NET4GAS company. A new 150-kilometer high-pressure gas pipeline was put into operation in January 2021, and the infrastructure under construction will strengthen the Czech Republic's and the entire CEE region with Western European gas markets, ensuring access to gas supplies at competitive prices, including access to planned terminals. for liquefied natural gas (LNG) in Germany.